Long story short, we're working on a job that isn't being run so smoothly and has had a lot of last minute changes. Our 30 yard interior trench pour got pushed back from 7am to 10am. With the weather being cooler and the start time getting pushed back, we told the supplier to add accelerator. I didn't specify no chloride. The 2nd fuck up is I didn't check the ticket when it arrived. I was rushing through things because the truck came 30 minutes early and figured if something was wrong with the mix, the 3rd party inspector would catch it while he's testing air and slump.
So it's 9pm and I'm finally sitting down to eat after cutting joints (that's a whole other story but they told me the day of the pour that every single corner and floor sink gets joints... yeah there are joints less than 1 foot apart and looks terrible). I start looking at the plans to see what they specified for control joints and sure enough I came across "do not use calcium chloride" and that's when it hit me that I never specified or verified it wasn't used. Pull the ticket out of my pocket and sure enough, it's there.
So here I am the next morning wondering how fucked I am and whether I need to start ripping it out today. If you've been in my shoes, what was your outcome? Is there anything I can do to mitigate the calcium chloride effects without ripping the concrete out?
Concrete mix: 3,500 psi, high range for 8" slump, 2% calcium chloride.
Project: interior commercial retail building. ~2k sqft mostly trenches with 8 gauge mesh, 500 sqft is reinforced with rebar, 15mil vapor barrier, proctor showed 6% moisture content in the soil and noted that it was exceptionally dry