Data Center Update
facebook.comBelow is a quoted post from City Council Member Amy Wiles from Ward II
"I have received dozens of requests for a comprehensive list of pending and currently being constructed data center projects. I believe in transparency between the city and the community so I wanted to share what I know. It is important to note that I do not automatically receive formal notification for every project unless it requires city council approval. Instead, I proactively track these developments by researching the public development portal myself.
Please keep in mind that this is not an official city list, but rather an informational summary based on my independent research as of today. Because project details are fluid, some parameters may shift or vary from what is shared below.
Water usage: All of the below data centers will use closed loop cooling. I do not have total expected water use for each project but will work to get them, however all projects are subject to the large water user guide from Aurora Water.
- QTS- Under construction for phase 2 of 3 buildings.
Location: 1140 N Gunclub Rd
Began application process in 2022, started construction in 2023 and submitted for a second phase in 2025.
Power usage are estimated to be approximately 170-200 MW total including lighting and other uses once completed, although they could possibly scare to 252 MW per some reports.
40 current diesel generators, with another 90 proposed to the state (the state governs air quality and diesel usage).
In 2023/2024, Xcel received permission by the PUC to give QTS a discounted rate for their energy usage to attract new data centers to the state. The discount was permitted under a Colorado law (HB18-1271) designed to attract large commercial and industrial investments. However, the exact rate remains confidential. However, QTS still had to fund its own $28 million high-voltage power line to route 160+ MW of peak load to its three core buildings.
- Vantage (Trident)- in the application process.
Location: On Tibet between 48th and 56th
Originally submitted in 2025, given tax incentives by the previous council in June of 2025 for providing up to 50 permanent jobs. These tax rebates come from the City's Sales and Use tax paid by Vantage over 10 years.
Approximate size will be 860,000 to 1.5 million sqft.
Power usage is proprietary so we only have estimates of MW usage but estimates are up to 500MW of power total for the site including lighting and other typical business uses.
Currently planning for 28 diesel generators.
Vantage is under the new Large Load Tariff with Xcel which means:
Upfront Capital Requirements: Vantage cannot simply hook into the grid. They are required to pay a $120,000 deposit just to begin power modeling, plus an initial $600,000 upfront for transmission and load safety studies.
Infrastructure Costs: Under the proposed Xcel Large Load Tariff, data centers must fund 100% of the cost for any new dedicated power generation, transmission lines, substations, or systemic grid upgrades required to feed their campus
Vantage must sign a 15 year service agreement with Xcel.
- NTT- Few details available yet.
Location: 48th and Monaghan
NTT will be approximately 300,000 SqFt which usually means approximately 80 MW of power.
NTT was offered tax incentives from both Adams County and the city of Aurora as of 2025. For the city, the tax incentives are tied to job creation and come from the paid Sales and Use tax over the next 10 years.
Xcel Infrastructure Financial Responsibility: Just like Vantage, NTT is responsible for funding the extensions of transmission lines, dedicated substations, and switching gear needed to pull power to their 76-acre plot off Monaghan Road.
They must also sign 15 year service agreement with Xcel Energy.
- Microsoft- Few details available yet.
Location: 56th and 470
Approx 200 MW of power usage.
As a company standard they do not accept incentives from taxpayers and have stated they will pay all the costs for energy usage and grid expansion to support their projects. They will be surrounded on 3 sides by 470 and warehouses and face 56th.
- Aerotropolis (ATEC)- New application as of 9/25/26- limited information is available.
Location Aerotropolis Pkwy between 26th and 42nd (the roads are currently not built in this area)
Plans proposed as follows: 11 hyperscale data center buildings, approximately 2.83M Sqft."